Project 13.

City gypsum factory

The duration of the project is 8 months at a cost of 2,500,000.

Establishing the factory in the industrial zone of Jabal Ataka, Suez, in cooperation with the Arab Swiss Company, ASEC.

Construction and finishing of the administrative building

Image
Project 14.

Ameryah cement factory

The duration of the project is 5 months at a cost of 4,200,000.

Implementing the alternative energy project in cooperation with the consultant RHI-RELIANCE HEAVY INDUSTRY.

Tank height of 17 linear meters with a flat surface of 500 meters

Implementation of the rest of the project tanks Work and finishing the power station Fully implement belt rules

Image
Project 15.

ASIC to protect the environment

The duration of the project is 6 months at a cost of 2,400,000.

Carrying out construction work for the ASEC plant for environmental protection, Aspenbro, in May 15th .

Image
Project 16.

Ministry of Commerce and Industry

Rehabilitation and finishing of the building for the sectors of foreign trade and trade agreements.